Yallourn Mine Alliance – Ash Pond Project (Annually)

Project Status: Ongoing

Yallourn Mine Alliance – Ash Pond Project (Annually)

Client: Energy Australia
Contract Type: Alliance / Cost Plus
Value: $2,000,000.00

200,000m3

Ash hauled annually

20+ years

Repeat annual work

4,000 man hours

Annually

4,000,000m3

Ash moved over the life of the project

Project Challenge

RTL’s was engaged to haul and dump Coal Ash from the localised Yallourn Mine Ash Ponds to the dump within the site. The works also entail the maintenance and management of haul routes, excavation and placement of clay for capping of bunds and drainage of wet ask from the pond to the recycle site.

RTL's Approach

RTL delivers this Project annually with its ongoing relationship with Energy Australia at Yallourn Mine with its specialised fleet of amphibious excavators and low load bearing dozers that are ideal for this bespoke Project.

Project Outcomes

1. Ongoing specific Ash Pond Project works for 20+ years at Yallourn Mine which makes RTL the contractor of choice for these works.

2. RTL is able to work with the ongoing Mine Operations and other site sub-contractors to complete these works.

3. RTL’s commitment to progressively rehabilitate mine sites across Australia.