RTL’s team was to divert the Morwell River as well as smaller diversions of Wilderness Creek and Eel Hole Creek as well as the adjacent Highway and Rural roads
RTL's Approach
A new alignment of the Strzelecki Highway and the Morwell River was required by the client to expand the open-cut mine at Hazelwood Power Station.
Project Outcomes
1. The project involved the placement of 10 million m³ of engineered fill used.
2. Relocation of 7.5km of the Strzelecki Highway included the construction of two bridges as well as all roadworks and drainage.
3. Re-routing of the existing OD9 route including upgrading 5km of rural roads.
4. Diversion of the Morwell River as well as smaller diversions of Wilderness Creek and Eel Hole Creek.