Project Overview
Exxon Mobil – Longford Gas Conditioning Plant
Project Status: Completed
Exxon Mobil – Longford Gas Conditioning Plant
Client: Exxon Mobil
Contract Type: Lump Sum
Value: $40,000,000.00
150,000m3
Earthworks
43,000m2
Plant road construction
10,000m2
Asphalting
15,000m3
HDPE lined stormwater pond
Project Challenge
RTL’s project involved earthworks, roads and drainage for the new Exxon Mobil Gas Conditioning Plant at Longford.
RTL's Approach
RTL successfully delivered throughout the project as the client continually expanded the scope of RTL’s work. This can be attributed to RTL’s ability to meet the client’s high-specification civil requirements.
Project Outcomes
1. RTL works included the construction of 700lm of in-situ concrete trench construction
2. RTL works included the construction 2,300lm of HDPE fire service main
3. RTL works included the construction of RCP drainage
4. RTL works included the construction of mesh security fencing